When budgets and schedules don’t match reality, Earned Value Management (EVM) gives a clear, objective view of project performance and forecasts final cost and schedule. Learn PV, EV, AC, CPI, and SPI, and use practical steps and tools to spot issues early and keep projects on track.
August 21, 2025 (2mo ago) — last updated October 24, 2025 (3d ago)
Earned Value Management (EVM): Guide & Metrics
Master PV, EV, AC, CPI, and SPI to forecast costs and schedules, spot risks early, and control project performance.
← Back to blog
Earned Value Management (EVM): Guide & Metrics
Author: (original author — unchanged)
Published: (original date — unchanged)
Introduction
When budgets and schedules don’t match reality, Earned Value Management (EVM) gives a clear, objective view of project performance1. This practical guide explains Planned Value (PV), Earned Value (EV), and Actual Cost (AC), and shows how to use the Cost Performance Index (CPI) and Schedule Performance Index (SPI) to forecast outcomes, spot issues early, and communicate progress to stakeholders.
Why EVM matters
Project managers worry about rising costs, slipping timelines, and uncertain progress. EVM connects scope, schedule, and cost into a single system so you can see where you are versus the plan and forecast where you’ll finish if current trends continue. Think of EVM as project navigation that shows your current position, pace, and likely arrival time.
What EVM answers (quick)
EVM answers three core questions:
- Where did we plan to be? (Planned Value — PV)
- Where are we actually now? (Earned Value — EV)
- What did it cost to get here? (Actual Cost — AC)
Combine PV, EV, and AC to surface issues early so you can act before problems escalate.
Core metrics and formulas
- Planned Value (PV): budgeted cost of work scheduled to date
- Earned Value (EV): budgeted cost of work actually completed (percent complete × BAC)
- Actual Cost (AC): money spent to date
Key formulas:
CV = EV - AC # Cost Variance
CPI = EV / AC # Cost Performance Index
SV = EV - PV # Schedule Variance
SPI = EV / PV # Schedule Performance Index
How to read them:
- CV < 0 → over budget; CV > 0 → under budget
- CPI < 1 → cost inefficiency; CPI > 1 → cost efficiency
- SV < 0 → behind schedule; SV > 0 → ahead of schedule
- SPI < 1 → slower than planned; SPI > 1 → faster than planned
Tip: watch trends, not just a single reading. One bad week doesn’t always indicate a systemic problem, but a downward trend does.
Simple example
Project: mobile app authentication feature
- Budget (BAC): $40,000
- Duration: 4 weeks
- End of Week 2: PV = $20,000, EV = $16,000 (40% complete), AC = $22,000
Calculations:
- CV = 16,000 - 22,000 = -6,000 → $6,000 over budget
- CPI = 16,000 / 22,000 = 0.73 → $0.73 earned per $1 spent
- SV = 16,000 - 20,000 = -4,000 → behind schedule (value-based)
- SPI = 16,000 / 20,000 = 0.80 → progressing at 80% of planned speed
With these metrics you can investigate root causes (scope creep, productivity, procurement) and apply targeted fixes: reassign resources, reduce scope, or negotiate costs.
Set up EVM practice the right way
-
Build a defensible baseline (PV / BAC)
- Use a three-point estimate (optimistic, most likely, pessimistic) to reduce bias.
- Don’t rely on wishful thinking — an inaccurate PV produces unreliable metrics.
-
Collect timely, accurate progress data
- Standardize percent-complete rules (milestone-based, earned hours, or value-based).
- Automate AC collection where possible from timesheets, invoices, or procurement systems.
-
Monitor CPI and SPI regularly
- Treat them as early-warning signals and follow trends rather than single values.
-
Re-baseline when approved scope changes occur
- Update BAC and the PV curve through formal re-baselining so metrics remain meaningful.
Tools that help
Make EVM actionable by replacing ad-hoc spreadsheets with focused tools and templates. These tools help with budgeting and contingency planning:
If you prefer to avoid external tools, a one-page baseline sheet that includes BAC, PV curve, EV rules, and AC sources is often enough to get started.
Related guides
- How to build a project baseline
- 3-point estimating: step-by-step
- Using contingency buffers to manage risk
- EVM vs Agile: When to use which
Common EVM questions (quick answers)
Is EVM only for large government projects?
No. EVM scales. Use a light-weight approach for small projects — track a few milestones and major cost categories — and a full EVM setup for complex programs.
How do scope changes get handled?
Through re-baselining. When scope changes are approved, update BAC and PV so EV, CPI, and SPI reflect the current authorized plan.
What tools help implement EVM?
Project management suites that support baseline tracking, time and expense integration, and percent-complete reporting are ideal. Supplement with calculators like the Construction Material Cost Predictor and the Event Planning Budget Allocator to tighten inputs.
Strategic payoffs of EVM
- Early detection of cost and schedule issues (CPI and SPI act as alarms)
- Better forecasting (Estimate at Completion — EAC — uses CPI to predict final cost)
- Clear, objective stakeholder communication — data replaces opinion
- Smarter resource decisions and protection of margins
Disciplined EVM often reduces cost overruns and improves delivery reliability2.
Recommended next steps (practical checklist)
- Set up a defensible PV using three-point estimating and document assumptions
- Automate AC collection (time tracking + expense imports)
- Decide EV rules: milestone-based, earned hours, or percent complete per deliverable
- Monitor CPI and SPI weekly; trigger root-cause analysis when either is below thresholds (for example, 0.95)
- Use a budget allocator or contingency approach to size corrective funds when needed
Further reading and resources
If you want a simple starter artifact, create a one-page baseline sheet with BAC, PV curve, EV rules, and AC sources. That often turns EVM from a concept into practical control.
Conclusion
EVM turns subjective progress reports into objective, actionable insight. Learn PV, EV, and AC, and use CPI and SPI to move from guessing to knowing. Start with a reliable baseline and simple calculators; over time EVM becomes a strategic advantage for predictable, profitable projects.
Quick Q&A: Common user questions
Q: How soon will EVM show problems? A: Early — if you collect reliable progress and cost data. CPI and SPI act as early-warning indicators once you have a defensible baseline.
Q: Can EVM work with Agile teams? A: Yes. Use sprint-level EV rules or value-based percent complete to align EVM with iterative delivery.
Q: What threshold should trigger action? A: Use a conservative trigger like 0.95 for CPI or SPI, then perform a root-cause analysis and corrective plan if the trend persists.